The client, Medical Centre Developments, appointed calfordseaden to provide Cost Consultant, Employer’s Agent, Health and Safety Advisor, and Structural Engineering services to develop a new primary care centre with a gross internal area of 1,343 square metres. The scheme provides 18 clinical rooms comprising 11 consulting rooms and seven treatment rooms plus ancillary administration patient reception areas.
Various challenges developed as the UK went into and came out of the imposed Government lockdown measures. The contractor was let down by their precast concrete subcontractor the day before the delivery of the flooring units was due, and reported that to obtain a replacement would cause a delay of circa six months. calfordseaden worked with the contractor to find a suitable alternative and proposed a posi-joist system. This was accepted and mitigated the delay by circa 50% and still met the primary care employer’s requirements.
The ancillary space was originally planned to be occupied by a separate pharmacy tenant, however, the GP practice taking the lease on the medical centre decided to lease this space as well. calfordseaden negotiated the additional fit out cost for this unit with the contractor without incurring a client delay on the completion of the project. There was sufficient time for these works to run concurrently alongside the main works.