calfordseaden was appointed by Smartparc Ltd to provide BIM Coordination services on the construction of a cold storage facility in SmartParc Plot 8, part of a 155 hectares high-tech food manufacturing campus. SmartParc Plot 8 is dedicated for Hello Fresh and includes a dedicated Energy centre for them as well.

We were appointed for RIBA Stages 3+, 4 and 5 and were chosen to deliver this part of the project due to our team’s extensive knowledge of the BIM Deliverables. calfordseaden provided these key elements to the scheme: BIM execution plan, responsibility matrix, Master Information Delivery Plans, COBie Data for each subcontractor, weekly clash detection tests, workshops and creating reports.

Alongside this, a BIM execution plan was created to ensure the client’s needs were satisfied to an exemplary standard. Clash detection tests were conducted weekly to detect issues prior to site arrival. This led to increased levels of efficiency when delegating roles.